Industrial/Natural Gas/CHP Case Study - Brea, California
Northeast Energy Systems & Western Energy Systems - Power Systems Specialists

Techni-Cast: Industrial/Natural Gas/CHP Case Study

With the efficiency of today’s cogeneration systems, at Western Energy Systems, we can often provide new equipment that significantly increases electrical efficiency while reducing emissions to meet stringent environmental regulations. A foundry in Los Angeles, Techni-Cast Corp., contacted us regarding their ten year old Jenbacher engine which provided 1060 kilowatts of power and was rated at 13 ppm for NOx emissions. The customer’s energy needs had increased and they were interested in installing a new system that would reduce their emissions output. We performed a feasibility analysis and detailed all of the changes that would be required to install a new generator set. After the plan was approved, a new Jenbacher JMC 420, which provides 1426 kilowatts of power with an emission rating of 5.5 ppm for NOx compounds, was installed. To accomplish this, the radiator had to be relocated from the top of the enclosure to across the street.

The cleaned exhaust stream is used to pre-heat a metal furnace to approximately 750° F, making this system very efficient. The water that is heated in the water jacket is used to feed the hot water fired chiller for additional process requirements in the facility. This system has an electrical efficiency of 41.9% and a total efficiency of 72.9% using the LHV calculation method, and meets all CARB 1110.2 compliance regulations with CEMS data. Because the system meets efficiency and emission requirements, it also qualified for the California Self-Generation Incentive Program, which further reduced the overall cost of the project. The customer has been very happy with the efficiency and reliability of the new system as well as the reduction in the noise level that it has provided. For additional details regarding this industrial cogeneration project, see the table below, or contact us directly.

How Can We Help You?

Industrial Cogeneration Case Study Highlights

Project Description
Upgraded from 1 x JCG 320 permitted at 13ppmv NOx, rated at 1060kw to 1 x JMC 420 permitted at 5.5ppmv NOx, and rated at 1426kw
Capabilities Applied/Processes
Primary:
New Generator Set Supply & Systems Integration
Secondary:
Up-front Technical Detail for Feasibility Analysis
Equipment Used
JMC 420-B85
Benefits/Advantages
  • Cleaned exhaust is provided directly to pre-heat metal furnace at ~750*F
  • Jacket water feeds hot water fired chiller for process needs onsite
Electrical Efficiency (LHV)
41.9%
Total Efficiency (LHV)
72.9%
Gas Type
Natural Gas
Special Features
Exhaust Heat Pre-Warms Metal
Delivery Location
Los Angeles, California
Standards Met
Meets or exceeds CARB 1110.2 with CEMS